Task
|
Hazards
|
Persons
at Risk
|
Unmitigated
Risk
|
Proposed Mitigation
Measures
|
Mitigated
Risk
|
|||||
L
|
S
|
R
|
L
|
S
|
R
|
|||||
mobilization
|
Falling
Hazard
|
mobilization
Team
|
4
|
5
|
20
|
·
All skilled labor
will use full body harness and 100% tie off and fixed point.
·
Only skilled labor
will be allowed to work at height.
·
All skilled labor
will use fall arrestor system.
`.
|
2
|
4
|
8
|
|
Falling
objects
|
Labours
|
3
|
5
|
15
|
·
A skilled watcher
will be existing.
·
Hard barrier to be
installed, signs and PPE.
|
1
|
4
|
4
|
||
Electric
shock
|
mobilization
Team
|
3
|
4
|
12
|
·
Disconnect all
Power Sources.
·
LOCK OUT TAG OUT
procedure will be applied.
·
Wearing PPE
against electric shock prior to commencing work
·
All used
equipments are properly grounded and daily checked
|
1
|
4
|
4
|
||
Dust
inhalation
|
Labours
|
4
|
2
|
8
|
·
All labour will Use dust
mask.
·
Dust control procedure
will be applied.
|
2
|
2
|
4
|
||
Releasing
steel rebar & wood
|
Material
handling
|
mobilization
Team
|
3
|
4
|
12
|
·
The material handling
will be done in correct method, Controlled by authorised personnel.
|
2
|
4
|
8
|
|
Waste materials.
|
Tripping
Hazard
|
Labours
|
5
|
3
|
15
|
·
Housekeeping will be done
immediately as soon as possible.
·
All nails to be removed from lumbers
assemblies.
|
2
|
3
|
6
|
|
Install
mobilized material
|
Crush hazard, Equipment movement & Trucks.
|
Labours
|
3
|
5
|
15
|
·
Barricades will be
applied around working area &signs.
·
Flag man will be exist.
|
2
|
4
|
8
|
|
Dust
inhalation
|
Labours
|
4
|
2
|
8
|
·
All labour will Use dust
mask.
·
Dust control procedure
will be applied.
·
Equipments &trucks to
be equipped with back alarm
|
2
|
2
|
4
|
||
Cutting Rebars
|
Burns,
Fire.
|
Welders/Operational
Team.
|
4
|
4
|
16
|
·
All equipment to be
checked and colour coded.
·
Equipment to be correctly
earthed.
·
Cutting work to be
controlled with hot work permit.
·
PPE
·
Fire extinguishers will
be available
|
2
|
4
|
8
|
|
Removal of scrap
|
Equipments
&Trucks
|
Labours
|
3
|
4
|
12
|
·
Controlled removal of
spoils” banks man “.
·
One way system of traffic
wherever possible.
·
Signs and signals to be
established to control traffic movement.
·
All vehicles will be
parked uniformly and in a suitable parking area
·
Parking area will be
provided by sheds from the sun
·
Arrange a suitable place
for fuel tanks, chemical tanks and other active materials containers away
from other facilities.
·
Arrange chemical powder
fire extinguishers.
|
2
|
4
|
8
|
|
Night work
|
Slips,
trips, falls and vehicle collisions.
|
Workers
|
3
|
4
|
12
|
·
Carry out work in
accordance with attached Night Work JHA.
·
Lightening will be
provided
|
2
|
4
|
8
|
|
mobilize
the ground floor
|
Noisy
|
Labours
|
5
|
2
|
10
|
·
All labour will use ear
muff.
|
2
|
3
|
6
|
|
L (Likelihood) X S (Severity)
= R (Risk)
|
If MITIGATED
RISK = UNMITIGATED RISK contact Safety Manager
|
|||||||||
1 ~ 5 X 1 ~ 5 = 1 ~ 25
|
Workforce
to be briefed with findings before work
|
|||||||||
Remark: all Labours
will wear PPE (hard hat, safety glasses, safety shoes, gloves, Dust mask)
1 -8 Low
Risk – Work can commence
9 -12 Medium
Risk – Reduce risk further or increase supervision
12 – 25 High
Risk – Must be mitigated