نماذج تقرير المخاطر


نماذج تقرير المخاطر 

Team Members


    1.      Eng. Wassef roushdy                 WD MATS. DEPT. HEAD.
    2.      MR. SALAH A/ LATIF                      WD RECEIVING DEPT. HEAD.
    3.      Eng. ASHRAF MAH. A/AZIZ             WD HSE
    4.      MR. MOHAMED FATHY                   WD HSE
                                                                   
19/5/2003

Risk Assessment

Subject: - LOADING CAR OF TRUCK

Step
What Can Go Wrong?

What Would Happen if it Did?

Risk Evaluation

What Can I Do to Prevent This?

Residual Risk

P
S
R.R
P
S
R.R
1
FALL OF THE CAR.
    ·  DAMAGE OF CAR.
    ·  ENJURY
H
H
13
    ·  CRANE AND SLINGS CHECKED CERTIFIED
    ·  DIRECT SUPERVISION
    ·  WATCHING PERSONNEL POSITION
    ·  USING PPE
L
L
2
 Remarks:-

Ø P   = Probability    

Ø S   = Severity     
Ø R.R= Risk Rating











Team Members                                                 Risk Assessment

Date: 30/3/2003

    5.      Eng. Magdy Alam                 WD Maint. Ass. Gen. Mgr.
    6.      Eng.: Moh. Mostafa              Const. Div.
    7.      Eng. Mahmoud A/Halim        WD HSE
    8.      Eng.: Alaa A/Maksod            PETROJET
                                                                   

Subject: -   Installing and connected A/G Incinerator

Step
What Can Go Wrong?

What Would Happen if it Did?

Risk Evaluation

What Can I Do to Prevent This?

Residual Risk

P
S
R.R
P
S
R.R
1
















FALL OF THE EQUIP.
    ·  DAMAGE OF EQUIP.
    ·  ENJURY
H
H
13
    ·  CRANE AND SLINGS CHECKED CERTIFIED
    ·  DIRECT SUPERVISION
    ·  WATCHING PERSONNEL POSITION
    ·  USING PPE
L
L
2
 Remarks:-

Ø P   = Probability    

Ø S   = Severity     
R.R= Risk Rating

Team Members

1.   MR. AHMED EDREES                      WD S. Service DEPT. HEAD.
2.   Eng. ASHRAF MAH. A/AZIZ             WD HSE
3.   MR. HAMDY TAWFEK                     WD HSE
                                                                

Risk Assessment

 

Date 18/5/2003

Subject: - Installed pole at airport using crane

Step
What Can Go Wrong?

What Would Happen if it Did?

Risk Evaluation

What Can I Do to Prevent This?

Residual Risk

P
S
R.R
P
S
R.R
1
FALL OF THE pole.
    ·  DAMAGE OF EQUIP.
    ·  ENJURY
H
H
13
    ·  CRANE AND SLINGS CHECKED CERTIFIED
    ·  DIRECT SUPERVISION
    ·  WATCHING PERSONNEL POSITION
    ·  USING PPE
L
L
2
 Remarks:-

Ø P   = Probability    

Ø S   = Severity     

Ø R.R= Risk Rating










Team Members

4.   Eng. ASHRAF MAH. A/AZIZ             WD HSE
5.   MR. HAMDY TAWFEK                     WD HSE
6.   MR. MOHAMWED FATHY                WD HSE
                                                                

Risk Assessment

 

Date 18/5/2003

Subject: - Drilling refilling breakage water using fire water pump 

Step
What Can Go Wrong?

What Would Happen if it Did?

Risk Evaluation

What Can I Do to Prevent This?

Residual Risk

P
S
R.R
P
S
R.R
1
Emergency case during refilling.
    ·  DAMAGE OF EQUIP.
    ·  ENJURY
H
H
13
    ·  Isolate the refilling water valve.

L
L
2
 Remarks:-

Ø P   = Probability    

Ø S   = Severity     
Ø R.R= Risk Rating